- Option to view the deviation of archived data from current data.
- Bulk update for Status Day.
See the difference between archived data and current data.
By default, the archived columns display the original archived data. This option allows you to see the difference between the archived data and the current data in the columns.
Status Day
Project plans need to be updated to reflect the current status or to prepare for reporting.
- In day-to-day project management, it is necessary to update the status of completion or to change the schedule for tasks that are currently delayed.
- In project communications, when reporting on the scheduled reporting day, it is desirable that the completion rate of all tasks match the scheduled completion rate for that day.
There are two options to batch updating tasks with unmet goals:
- Change the task completion rate to match the target completion rate for the report day.
- Change the task start time to match the target completion rate for the report day and the current completion rate. And some other tasks linked with them will be changed to meet the link constraints.